Shop Overhead Cranes PlaybookNow
In large construction and fabrication spaces, overhead/bridge cranes do the heavy lifting—literally. This long-form walkthrough shows how a full overhead crane system comes to life inside a structural building. You’ll see structural checks, safety, and QA/QC—with the same checklists pro installers use.
Bridge Crane Basics
An overhead crane rides on parallel runways anchored to a building frame, with a trolley that travels left-right along the bridge and a hoist that lifts the load. The system delivers three axes of motion: and lift via the hoist.
They’re the backbone of heavy shops and assembly lines, from steel frame construction beam handling to turbine assembly.
Why they matter:
Controlled moves for large, expensive equipment.
Huge efficiency gains.
Repeatable, precise positioning that reduces damage.
High throughput with fewer ground obstructions.
What This Install Includes
Runways & rails: runway girders with crane rail and clips.
End trucks: motorized gearboxes for long-travel.
Bridge girder(s): single- or double-girder configuration.
Trolley & hoist: cross-travel carriage with lifting unit.
Electrics & controls: VFDs, radio remote, pendant.
Stops, bumpers & safety: overload protection, e-stops.
Depending on capacity and span, you may be dealing with modest shop lifts or major industrial picks. The choreography is similar, with heavier rigs demanding extra controls and sign-offs.
Pre-Install Prep
A clean install is mostly planning. Key steps:
Drawings & submittals: Approve general arrangement (GA), electrical schematics, and loads to the structure.
Permits/JSAs: Permit-to-work, hot work, working at height, rigging plans.
Runway verification: Survey columns and runway beams for straightness, elevation, and span.
Power readiness: Confirm conductor bars or festoon supports, cable trays, and isolation points.
Staging & laydown: Mark crane components with ID tags.
People & roles: Appoint a lift director, rigger, signaler, and electrical lead.
Tiny survey errors balloon into hours of rework. Spend time here.
Getting the Path Right
Runway alignment is the foundation. Targets and checks:
Straightness & elevation: shim packs under clips to meet tolerance.
Gauge (span) & squareness: Use feeler gauges on splice bars, torque rail clips.
End stops & buffers: Install and torque per spec.
Conductor system: Mount conductor bars or festoon track parallel to the rail.
Record as-built readings. Correct now or pay later in wheel wear and motor overloads.
Girder Erection & End Trucks
Rigging plan: Choose spreader bars to keep slings clear of electricals. Dedicated signaler on radio.
Sequence:
Lift end trucks to runway level and set temporarily on blocks.
Rig the bridge girder(s) and make the main lift.
Land the bridge on the end trucks and pin/bolt per GA.
Verify camber and bridge square.
Before anyone celebrates, bump-test long-travel motors with temporary power (under permit): confirm limit switch wiring. Re-apply LOTO once checks pass.
Cross-Travel Setup
Trolley installation: Hoist/trolley arrives pre-assembled or as modules.
Hoist reeving: Lubricate wire rope; verify dead-end terminations.
Limits & load devices: Check overload/SLI and emergency stop.
Cross-travel adjustment: Align trolley rails on a double-girder.
Pendant/remote: Install pendant festoon or pair radio receiver; function-test deadman and two-step speed controls.
A smooth trolley with a quiet hoist is a sign of good alignment. Fix the mechanics first.
Power with Discipline
Power supply: Drop leads tagged and strain-relieved.
Drive setup: Enable S-curve profiles for precise positioning.
Interlocks & safety: Zone limits near doors or mezzanines.
Cable management: Keep loops short, add drip loops where needed.
Future you will too. If it isn’t documented, it didn’t happen—put it in the databook.
ITP, Checklists, and Sign-Off
Inspection Test Plan (ITP): Hold/witness points for rail alignment, torque, electrical polarity, limit settings.
Torque logs: Re-check after 24 hours if required.
Level & gauge reports: Attach survey prints.
Motor rotation & phasing: Document bump tests.
Functional tests: Anti-collisions and zone interlocks.
QA/QC is not paperwork—it’s your warranty in a binder.
Proving the System
Static load test: Hold at mid-span and near end stops; monitor deflection and brake performance.
Dynamic load test: Travel long-run, cross-travel, and hoist at rated speed with test load.
Operational checks: Emergency stop shuts down all motions.
Training & handover: Maintenance intervals for rope, brakes, and gearboxes.
Only after these pass do you hand over the keys.
Everyday Heavy Lifting
Construction & steel erection: placing beams, trusses, and precast.
Oil & gas & power: moving heavy pumps, skids, and pipe spools.
Steel mills & foundries: hot metal handling (with the right duty class).
Warehousing & logistics: high throughput lanes.
Floor stays clear, production keeps flowing, and precision goes up.
Controls that Matter
Rigging discipline: rated slings & shackles, correct angles, spreader bars for load geometry.
Lockout/Tagout: clear isolation points for electrical work.
Fall protection & edges: approved anchor points, guardrails on platforms, toe boards.
Runway integrity: regular runway inspection plan.
Duty class selection: match crane class to cycles and loads.
A perfect lift is the one nobody notices because nothing went wrong.
Troubleshooting & Pro Tips
Crab angle/drift: verify end-truck wheel diameters and gearbox mounts.
Hot gearboxes: adjust brake air gap and reduce VFD decel.
Rope drum spooling: check fleet angle and sheave alignment.
Pendant lag or dropout: shield noisy VFD cables.
Wheel wear & rail pitting: lubrication and alignment issues.
A 10-minute weekly check saves days of downtime later.
Quick Answers
Overhead vs. gantry? Choose per site constraints.
Single vs. double girder? Singles are lighter and cheaper; doubles carry heavier loads and give more hook height.
How long does install take? Anything from a couple weeks to a few months.
What’s the duty class? FEM/ISO or CMAA classes define cycles and service—don’t guess; size it right.
Who Gets the Most Value
Students and pros alike get a front-row seat to precision rigging, structural alignment, and commissioning. You’ll gain a checklist mindset that keeps cranes safe and productive.
Need a field bundle with JSA templates, rigging calculators, and commissioning sheets?
Grab the installer pack so your next crane goes in cleaner, faster, and right the first time. Save it to your site tablet for quick reference.
...